1.每次装料前用水冲洗进料口,使进料口在装料时保持湿润
Flush the feed inlet with water before each loading to keep it moist during loading
2.在装料的同时向随车自带的清洗用水水箱中注满水
Fill the cleaning water tank with water while loading
3.装料后冲洗进料口,洗净进料口附近残留的混凝土
After loading, wash the feed port, and clean the remaining concrete near the feed port
4.到工地卸料后,冲洗出料槽,然后向混凝土贮罐内加清洗用水30—40 L;在车辆回程时保持混凝土贮罐正向慢速转动
After unloading at the construction site, wash the discharge tank, and then add 30-40 l of cleaning water into the concrete storage tank; keep the concrete storage tank in forward and slow rotation when the vehicle returns
5.下次装料前切记放掉混凝土贮罐内的污水
Remember to drain the sewage in the concrete tank before the next loading
6.每天收工时清洗混凝土贮罐及进出料口周围,保证不粘有水泥及混凝土结块
At the end of each day, clean the concrete storage tank and the area around the material inlet and outlet to ensure that there is no cement and concrete caking